Meeting Notes: June 2024 Fort Negley Park Redevelopme
Date: June 2024
Presenter: Richie Jones from HDL Lake (architectural/engineering firm)
Key Points:
Fort Negley is undergoing a major redevelopment project
Total project budget: $45-55 million
Phase 1 budget: $12 million
Timeline:
Design completion: Next 5 months
Bidding: Around December 2024/January 2025
Groundbreaking: Spring 2025
Project Overview:
Goal: Create an open-air museum of national significance
Extensive community engagement conducted (41+ stakeholder meetings, 3 public meetings)
Master plan focuses on preserving history, revealing untold stories, and connecting with community
Key elements:
New Bass Street Plaza to interpret historic neighborhood
ADA accessible pathways to fort
Memorial wall
Reinterpreted fort interior
New visitor/interpretive center (future phase)
Memorial lawn
Adventure playground
Improved connections to surrounding areas
Phase 1 Priorities:
Bass Street Plaza (with archaeological work)
Memorial lawn
New park entry/"Freedom Plaza"
Fort reinterpretation
New lighting for fort
Next Steps:
Another public meeting planned for late August/early September 2024
Fundraising efforts underway to supplement public funding
Questions/Discussion:
Parking plans
Connections to nearby sites (Adventure Science Center, City Cemetery)
Accessibility improvements
Programming opportunities
The presenter emphasized the historical and cultural significance of Fort Negley, describing it as potentially one of the most important cultural landscapes in the southeast or nation.